Chinese New Year falls on 6 February 2027, almost two weeks earlier than this year. If any of your parts ship from China, the safe window to order closes in December, not January.
That's the whole post in two sentences. The rest is why, and what to do about it.
Why does an early Chinese New Year matter?
Because the holiday itself is the shortest part of the disruption.
Factories start winding down one to two weeks before the date, as workers travel home. After the holiday, output takes weeks to recover, because not everyone comes back on schedule. Seko Logistics describes the whole thing as a six-to-eight-week window, running from early January to mid-March, and advises shippers to confirm bookings at least four weeks before shipment.
An early holiday squeezes that window into the year-end peak. Freight capacity is already tight in December. Add a pre-holiday rush from every buyer who's done the same maths, and space on planes and ships gets expensive fast.
What are we seeing on China freight right now?
Slower, pricier, and less predictable. Shipments out of China are taking longer than they did a few months ago, and batteries in particular face stricter inspections and airline dangerous goods rules. More on that in a couple of weeks.
For a South African manufacturer, the delay doesn't stop at the port of origin. You've still got transit, customs clearance, and a rand that may have moved by the time the goods land. Landed cost, not the quote, is the number that hurts.
When should I place my Q1 orders?
Earlier than feels comfortable. Here's the rough timeline we're working to:
Mid-December: last practical point to place orders for parts you need in February and March.
Late January: Chinese factories start winding down.
6 February: Chinese New Year.
Late February to mid-March: factories slowly back to full output, with a backlog to clear.
Anything ordered in January is competing with everyone else's panic orders for a shrinking slice of capacity.
What we'd do this week
List every China-sourced line on your BOMs that you'll need between January and March. Include the boring ones. A missing R2 resistor stops a line just as well as a missing MCU.
Pull those orders forward. Even a partial order now beats a full one in late January.
Send us your forecast for the first quarter. If we know what's coming, we can book space and secure stock ahead of the rush, instead of chasing it in February.
Isn't ordering early just tying up cash?
A little, yes. But compare it with the alternative: a line standing still in March, waiting on a part that left the factory late, sat in a congested port, and then queued at customs. Holding a few weeks of extra stock is usually cheaper than a single day of downtime.
It's the same lesson every shortage has taught us since 2010. The buyers who plan ahead aren't the lucky ones. They're the ones at the front of the queue.
Let's get your Q1 sorted
Send your forecast to info@sevenlabs.co.za, or straight to your account manager. We'll tell you which lines are at risk over the holiday and get them moving now.